Complementary user entity controls, or CUECs, are controls that your customers, called user entities, must have in place for the controls in your SOC 1 or SOC 2 report to meet the control objectives or criteria. Your management identifies them, the system description lists them, and the auditor's opinion assumes your customers apply them. A customer reading your report checks each CUEC against its own controls.
An example
You run a software application with single sign-on. Your controls restrict customer data to authenticated users, and you test them. Your customer's administrators decide who at the customer gets an account and when it is removed. So your report lists a CUEC such as: "User entities are responsible for granting, reviewing, and removing access for their own users of the application."
If a customer never removes a departed employee's account, your controls cannot stop that person from signing in. The CUEC tells the customer that this part of the control is theirs.
Where CUECs appear in a report
The system description lists the CUECs, usually near the end, and often maps each one to the criterion or control objective it supports. The auditor's opinion then states that your controls would meet the criteria or objectives if user entities applied the complementary controls assumed in the design of your controls. The auditor does not test your customers' controls. The opinion is conditional on them.
CUECs vs complementary subservice organization controls
Your report can list a second kind of complementary control, for the vendors you rely on.
| CUECs | Complementary subservice organization controls | |
|---|---|---|
| Who runs them | Your customers | Your vendors, such as your cloud provider or data center |
| Where they appear | The system description | The system description, with each vendor's name and service |
| How the auditor treats them | Assumed in the opinion and not tested | Under the carve-out method, assumed and not tested. Under the inclusive method, the vendor's controls are described and tested instead |
| Our price | Included | Carve-out included. Inclusive testing is $1,500 for each vendor |
Most reports use the carve-out method, because a large cloud provider will not let its customers' auditors test its controls. Under the carve-out method, you monitor the vendor, usually by reviewing its own SOC report, and we test that monitoring.
How management writes good CUECs
Management identifies the CUECs, and the auditor evaluates whether the description presents them fairly. A useful list has three traits.
- Each CUEC ties to a criterion or objective your controls cannot meet alone. If your controls meet the criterion without the customer's help, it is not a CUEC.
- Each CUEC names a specific action. "User entities are responsible for reviewing the access rights of their users" tells the customer what to do. "User entities are responsible for their own security" tells them nothing.
- The list is short. Customers' reviewers read every line, and a long list of generic CUECs reads as an attempt to shift responsibility.
A control you should run cannot become a CUEC. If your system is the only place a control can operate, moving it to the customer leaves the criterion unmet, and the auditor will challenge it.
How customers use CUECs
If you are reading a vendor's SOC report, the CUEC section is your work list.
- Find the CUEC section in the system description.
- For each CUEC, identify your own control that does the work, or decide that the CUEC does not apply to how you use the service.
- Record the mapping in your vendor review file.
- Fix any CUEC you cannot meet, or record the risk you accept.
For a SOC 1, your own financial statement auditor will ask for this mapping. For a SOC 2, your security team uses it to show that the vendor's controls and yours work together.
Questions
Does every SOC report have CUECs?
Most do, because almost every service depends on something the customer controls, such as who has access. A report with no CUECs is uncommon and worth a question to the vendor.
Can a customer rely on a report if it does not meet a CUEC?
It can rely on the report only in part. The vendor's controls still operate, but the criterion or objective the CUEC supports is not fully met for that customer. The customer should record the gap and decide how to cover it.
Do CUECs change between Type 1 and Type 2?
No. The list belongs to the system description, which both report types include.