What it means
ISO/IEC 27005 defines risk acceptance as an "informed decision to take a particular risk." It is one of four responses to a risk, alongside avoiding, reducing, and sharing it, and the SOC 2 risk assessment criteria name the same four choices. An acceptance holds up when the person making it has the authority to make it, knows the residual rating and the controls behind it, and applies criteria written down in advance. An acceptance can also be temporary, such as accepting a risk until a planned control goes live, with an expiry date that forces a new decision.
Where it shows up in an audit
In an ISO 27001 internal audit, the auditor tests acceptance against three requirements: risk acceptance criteria set under clause 6.1.2, a risk owner named for each risk, and the risk owners' acceptance of residual risks under clause 6.1.3. The evidence is the register entry or acceptance form showing the risk, the residual rating, the approver, the date, and the criteria applied.
In a SOC 2, we read accepted risks as part of criterion CC3.2, check each one against the policy's thresholds, and for a Type 2 look for reviews dated inside the observation period. Accepting a risk leaves the system description's commitments in force: if the description says access is removed within one business day, a late removal is still an exception.
Example
A SaaS company's legacy reporting server cannot run its endpoint detection agent until a migration finishes in the third quarter of 2026. On February 3, 2026, the risk owner, the vice president of engineering, records an acceptance with a residual score of 6 against a threshold of 8, two compensating measures (network isolation and weekly log review), and an expiry of September 30, 2026. The ISO 27001 internal auditor confirms that the owner is named in the register, the score meets the criteria, and the expiry is tracked.
What we see in audits
The acceptance records we question most often have no expiry date, so a risk accepted for a three-month migration stays accepted years later. An expiry date with a review reminder prevents it.
Related terms
- Residual risk: what the risk owner accepts.
- Risk appetite: the limit an acceptance must stay within.
- Risk treatment plan: the alternative to accepting a risk.
- Compensating control: measures often cited in an acceptance.
- Risk register: where acceptances are recorded.